Market Notices

122313RECLASSIFY CONTINGENCY20/12/2024 02:50:31 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 20/12/2024 14:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122296PRICES SUBJECT TO REVIEW20/12/2024 07:25:19 AM

[EventId:202412200730_review] Prices for interval 20-Dec-2024 07:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0725 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122295PRICES SUBJECT TO REVIEW20/12/2024 07:20:21 AM

[EventId:202412200725_review] Prices for interval 20-Dec-2024 07:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0720 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122294PRICES SUBJECT TO REVIEW20/12/2024 07:15:21 AM

[EventId:202412200720_review] Prices for interval 20-Dec-2024 07:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0715 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122293PRICES SUBJECT TO REVIEW20/12/2024 07:10:22 AM

[EventId:202412200715_review] Prices for interval 20-Dec-2024 07:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0710 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122292PRICES SUBJECT TO REVIEW20/12/2024 07:05:21 AM

[EventId:202412200710_review] Prices for interval 20-Dec-2024 07:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0705 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122291PRICES SUBJECT TO REVIEW20/12/2024 07:00:19 AM

[EventId:202412200705_review] Prices for interval 20-Dec-2024 07:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0700 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122288RECLASSIFY CONTINGENCY19/12/2024 08:19:25 PM

Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Cancellation time: 19/12/2024 20:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122257

Auto-generated on behalf of Manager NEM Real Time Operations
     
122287RECLASSIFY CONTINGENCY19/12/2024 08:19:20 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/12/2024 20:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122258

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm