Filter by category
Filter by Date
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024
The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116440 has been updated at 1745 hrs 02/05/2024 to the following:
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1146 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 888 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.115593 is cancelled at 1945 hrs 11/03/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 498 MW
The minimum capacity reserve available is 255 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115374 is cancelled at 1900 hrs 29/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1001 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115370 is cancelled at 1545 hrs 29/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1500 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1066 MW
Manager NEM Real Time Operations
Request for Generator Recall Information for 29/02/2024 for QLD Region
Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.
Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations