Market Notices

119690INTER-REGIONAL TRANSFER31/10/2024 01:00:29 AM

Inter-regional transfer limit variation - Wagga B 330 kV Bus - NSW region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Wagga B 330 kV bus- NSW region - 31/10/2024

At 0028 hrs 31/10/2024 there was an unplanned outage of Wagga B 330 kV bus.

The following constraint set(s) invoked at 0045 hrs 31/10/2024
N-WAGGA_330_BUSB, N-JNWG_RADIAL, V-DBUSS_L and V-DBUSS_T

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119688INTER-REGIONAL TRANSFER30/10/2024 06:15:38 PM

Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024

A planned outage of Moorabool - Sydenham No.1 500 kV line in the VIC region was scheduled from 0500 hrs 22/10/2024 to 1930 hrs 01/11/2024.

The outage has been completed and Moorabool - Sydenham No.1 500 kV line returned to service at 1815 hrs 30/10/2024

Constraint set revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
119626INTER-REGIONAL TRANSFER29/10/2024 11:27:47 AM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 119610

Constraint set CA_SYDS_5632AA58 was invoked from 0940 hrs until 10:45 hrs 29/10/2024.

This constraint set contains equations with the following interconnector on the LHS;
V-SA

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
119610INTER-REGIONAL TRANSFER29/10/2024 09:46:29 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_5632AA58 from 0940 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;
V-SA

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
119567NON-CONFORMANCE28/10/2024 12:55:17 PM

NON-CONFORMANCE Region SA1 Monday, 28 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 28 October 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 28/10/2024 12:05 to 28/10/2024 12:55
Amount: 39 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119500NON-CONFORMANCE27/10/2024 03:40:21 PM

NON-CONFORMANCE Region NSW1 Sunday, 27 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 27 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 27/10/2024 15:35 to 27/10/2024 15:40
Amount: -78 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
119499MARKET SYSTEMS27/10/2024 03:30:17 PM

CHG0098814 | Completed | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS and eMDM November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119458NON-CONFORMANCE26/10/2024 07:25:16 PM

NON-CONFORMANCE Region VIC1 Saturday, 26 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 26 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 26/10/2024 19:15 to 26/10/2024 19:25
Amount: -25 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119372NON-CONFORMANCE25/10/2024 09:15:15 AM

NON-CONFORMANCE Region NSW1 Friday, 25 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 25 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 25/10/2024 08:30 to 25/10/2024 09:15
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm