Direction - SA region 16/12/2024
Direction - SA region 16/12/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 16/12/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 121963
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 17/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 16/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 16 December 2024
NON-CONFORMANCE QLD1 Region Monday, 16 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 16/12/2024 02:20 to 16/12/2024 03:30
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 16 December 2024
NON-CONFORMANCE QLD1 Region Monday, 16 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 17/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 15 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 15 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 15/12/2024 10:45 to 15/12/2024 10:55
Amount: 11 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 15 December 2024
NON-CONFORMANCE QLD1 Region Sunday, 15 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 15/12/2024 09:00 to 15/12/2024 09:10
Amount: 11 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 13 December 2024
NON-CONFORMANCE QLD1 Region Friday, 13 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121818 is cancelled at 1200 hrs on 13/12/2024.
No LOR3 condition is currently forecast in the STPASA period.