Market Notices

117729MARKET INTERVENTION20/08/2024 03:31:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAND

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117718

TORRB3 TORRENS ISLAND end time update.

This update is issued at 1530 hrs 20/08/2024 and is expected to stay in place until 1630 hrs 20/08/2024

Manager NEM Real Time Operations
117722MARKET INTERVENTION19/08/2024 03:52:08 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAND

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117721

TORRB4 TORRENS ISLAND end time update.

This update is issued at 1530 hrs 19/08/2024 and is expected to stay in place until 1230 hrs 21/08/2024

Manager NEM Real Time Operations
117721MARKET INTERVENTION19/08/2024 02:58:52 PM

Direction - TORRB4 TORRENS ISLAND

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 19/08/2024

Refer to Market Notice 117714


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1500 hrs 19/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0030 hrs 21/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 21/08/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117720MARKET INTERVENTION19/08/2024 03:31:30 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117713

Direction is cancelled from: 1530 hrs 19/08/2024

Manager NEM Real Time Operations
117719MARKET INTERVENTION19/08/2024 02:33:56 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAND

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117712

TORRB2 TORRENS ISLAND end time update.

This update is issued at 1430 hrs 19/08/2024 and is expected to stay in place until 1630 hrs 20/08/2024

Manager NEM Real Time Operations
117718MARKET INTERVENTION19/08/2024 02:32:46 PM

Direction - TORRB3 TORRENS ISLAND

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 18/08/2024

Refer to Market Notice 117711

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAND at 1430 hrs 19/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 2330 hrs 19/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 21/08/2024 .

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
117717MARKET INTERVENTION19/08/2024 02:31:40 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAND

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117715

TORRB3 TORRENS ISLAND end time update.

This update is issued at 1430 hrs 19/08/2024 and is expected to stay in place until 1530 hrs 19/08/2024

Manager NEM Real Time Operations
117715MARKET INTERVENTION19/08/2024 08:36:05 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY PARTICIPANT NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 117713

TORRB3 TORRENS ISLAN at 0930 hrs 19/08/2024 to remain synchronised and follow dispatch targets.

This update is issued at 0830 hrs 19/08/2024 and is expected to stay in place until 0400 hrs 20/08/2024

Manager NEM Real Time Operations
117714MARKET INTERVENTION18/08/2024 04:19:18 PM

Direction - SA region 18/08/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 18/08/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 18/08/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
X