CHG0089701 | Completed | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0089701 | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Change Start Date & Time: 30/05/2024 09:00:00 AEST
Change End Date & Time: 30/05/2024 12:00:00 AEST
Outage Start Date & Time: 30/05/2024 09:00:00 AEST
Outage End Date & Time: 30/05/2024 12:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0089701 | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 30 May until 12pm (EST)
Change Start Date & Time: 30/05/2024 09:00:00 AEST
Change End Date & Time: 30/05/2024 12:00:00 AEST
Outage Start Date & Time: 30/05/2024 09:00:00 AEST
Outage End Date & Time: 30/05/2024 12:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Direction - SA region 28/05/2024
Direction - SA region 28/05/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1415 hrs on 28/05/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116824
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 29/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1400 hrs 28/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 29/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
RESERVE NOTICE MT PASA PUBLICATION 28 May 2024
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 116791 published on 23 May 2024.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National
Forecasting
AEMO
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National
Forecasting
AEMO
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1830 hrs 03/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1751 MW.
AEMO Operations
Cancellation - Possible intervention to manage power system security in SA region 28/05/2024
Cancellation - Possible intervention to manage power system security in SA region 28/05/2024
Refer Market Notice 116819
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1435 hrs 27/05/2024.
Manager NEM Real Time Operations