Filter by category
Filter by Date
Network Augmentation Commissioned - NSW Region - 16/08/2024
Network Augmentation Commissioned - NSW Region - 16/08/2024
Commissioned: Munmorah - Waratah S BESS 2Y 330 kV Line
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 15/08/2024
Network Augmentation Commissioned - NSW Region - 15/08/2024
Commissioned: Munmorah - Waratah S BESS 2W 330 kV Line
Manager NEM Real Time Operations
Planned outage of Nebo to Broadsound no. 8846 275 kV line in the QLD region beginning on 16/08/2024
The Nebo to Broadsound no. 8846 275 kV line in the Queensland (QLD) region is planned to be out of service from 0600 hrs 16/08/2024 to 1700 hrs 18/08/2024.
This outage is considered a High Impact Outage (HIO) as the outage recall is greater than 30 minutes.
A credible contingency event during this planned outage may require market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
QNI Minor testing (NSW to Qld) 12th August 2024
Refer to market notice 116052
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - VIC Region - 07/08/2024
Network Augmentation Commissioned - VIC Region - 07/08/2024
Cressy - Golden Plains No. 2 220 kV Line has been commissioned.
Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - VIC Region - 30/07/2024
Network Augmentation Commissioned - VIC Region - 30/07/2024
Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:
Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line
Manager NEM Real Time Operations
Network Augmentation Commissioned - VIC Region - 18/07/2024
Network Augmentation Commissioned - VIC Region - 18/07/2024
At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:
Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line
Manager NEM Real Time Operations
Load Shedding Direction in the NSW Region
Load Shedding Direction in the NSW Region
AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region
to maintain power system security.
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations