Update - AEMO Intervention Event - VIC region 14/11/2024
Update - AEMO Intervention Event - VIC region 14/11/2024
Refer to Market Notice 120420
The AEMO Intervention Event and all associated directions are NOT cancelled from 1700 hrs on 14/11/2024.
The AEMO Intervention event and all associated directions are continuing.
Manager NEM Real Time Operations
[EventId:202411141645_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 November 2024 16:45
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 14 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 November 2024.
Refer to market notice: 120437
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1645 hrs on 14 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411141630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 November 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 14 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 14 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2
Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2
Refer AEMO Electricity Participant Notice 120428
The MURR2-3 MURRAY2 direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2
Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2
Refer AEMO Electricity Participant Notice 120427
The MURR2-2 MURRAY2 direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120426
The JLB02 JEERALANG B PO direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120425
The JLB01 JEERALANG B PO direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120429
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 14/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 15/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1630 hrs 15/11/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120429
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 14/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 15/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 15/11/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations