120429MARKET INTERVENTION14/11/2024 02:52:58 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 120415

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 15/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 14/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
120428MARKET INTERVENTION14/11/2024 02:51:44 PM

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

Refer AEMO Electricity Participant Notice 120408

The MURR2-3 MURRAY2 direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120427MARKET INTERVENTION14/11/2024 02:50:41 PM

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

Refer AEMO Electricity Participant Notice 120407

The MURR2-2 MURRAY2 direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120426MARKET INTERVENTION14/11/2024 02:49:20 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120406

The JLB02 JEERALANG B PO direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120425MARKET INTERVENTION14/11/2024 02:47:55 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120405

The JLB01 JEERALANG B PO direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120423MARKET INTERVENTION14/11/2024 06:00:31 PM

Cancellation - AEMO Intervention Event - SA region 13/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 13/11/2024

Refer to Market Notice 120363

The AEMO Intervention Event and all associated directions are cancelled from 1800 hrs on 14/11/2024.


Manager NEM Real Time Operations
     
120422MARKET INTERVENTION14/11/2024 05:59:16 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 120412

Direction is cancelled from: 1800 hrs 14/11/2024

Manager NEM Real Time Operations
     
120421MARKET INTERVENTION14/11/2024 05:18:08 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120376

Direction is cancelled from: 1700 hrs 14/11/2024

Manager NEM Real Time Operations
     
120420MARKET INTERVENTION14/11/2024 04:52:42 PM

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - VIC region 14/11/2024

Refer to Market Notice 120404

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 14/11/2024.


Manager NEM Real Time Operations
     