122632RECLASSIFY CONTINGENCY31/12/2024 02:08:30 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 31/12/2024 14:08 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
122629PRICES UNCHANGED31/12/2024 01:34:24 PM

[EventId:202412311310_confirmed] Prices for interval 31-Dec-2024 13:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:10.

In accordance with Market Notice 122617 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122628PRICES UNCHANGED31/12/2024 01:33:14 PM

[EventId:202412311330_confirmed] Prices for interval 31-Dec-2024 13:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:30.

In accordance with Market Notice 122623 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122627PRICES UNCHANGED31/12/2024 01:39:05 PM

[EventId:202412311325_confirmed] Prices for interval 31-Dec-2024 13:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:25.

In accordance with Market Notice 122622 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122626PRICES UNCHANGED31/12/2024 01:32:00 PM

[EventId:202412311320_confirmed] Prices for interval 31-Dec-2024 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:20.

In accordance with Market Notice 122620 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122625PRICES UNCHANGED31/12/2024 01:30:24 PM

[EventId:202412311315_confirmed] Prices for interval 31-Dec-2024 13:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:15.

In accordance with Market Notice 122619 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122624PRICES UNCHANGED31/12/2024 01:37:22 PM

[EventId:202412311305_confirmed] Prices for interval 31-Dec-2024 13:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 31 December 2024

PRICES ARE NOW CONFIRMED for trading interval 31-Dec-2024 13:05.

In accordance with Market Notice 122615 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
122618RECLASSIFY CONTINGENCY31/12/2024 01:08:34 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 31/12/2024 13:08 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
122613RECLASSIFY CONTINGENCY31/12/2024 12:48:59 PM

Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge No.7184 and Kamerunga - Barron Gorge No.7143 132kV lines in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge No.7184 and Kamerunga - Barron Gorge No.7143 132kV lines

Duration: 31/12/2024 12:50 until further notice

Constraint set(s) invoked:
NONE

Manager NEM Real Time Operations