Market Notices

114714NON-CONFORMANCE14/02/2024 02:10:25 PM

NON-CONFORMANCE Region NSW1 Wednesday, 14 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 14 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SUNRSF1
Duration: 14/02/2024 08:55 to 14/02/2024 14:10
Amount: 91 MW
Constraint: NC-N_SUNRSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114685POWER SYSTEM EVENTS13/02/2024 10:37:34 PM

Update: Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

At 1827 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region, the following plant was returned to service.

The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer

The Jeeralang - Hazelwood No 2 220kV line remains out of service.

Refer to Network outage scheduler (NOS) for further details.

Refer Market notice 114641 and 114643

This Market Notice is issued in accordance with NER clause 4.8.3.


Manager NEM Real Time Operations
114669NON-CONFORMANCE13/02/2024 05:52:22 PM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TORRB4
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 14 MW
Constraint: NC-S_TORRB4

Auto-generated on behalf of Manager NEM Real Time Operations
114668NON-CONFORMANCE13/02/2024 05:51:32 PM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 20 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114643POWER SYSTEM EVENTS13/02/2024 04:13:14 PM

Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

At 1543 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region the following plant tripped.

The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer
The Jeeralang Hazelwood No2 220kV line.

Refer Market notice 114641

Updates will be provided as additional information becomes available.

This Market Notice is issued in accordance with NER clause 4.8.3.


Manager NEM Real Time Operations
114642POWER SYSTEM EVENTS13/02/2024 04:14:12 PM

Non-credible contingency event - TAS region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 13/02/2024

At 1602 hrs the Norwood -Scottsdale 110kV line and the Norwood - Scottsdale -Derby 110kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised 8MW of electrical load and 24MW of generation has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
114625POWER SYSTEM EVENTS13/02/2024 03:06:04 PM

Significant power system event - Victoria region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE.

At 1308 hrs 13/02/2024 the Moorabool Sydenham No1 and No2 500 kV lines tripped.
There have been reports of towers on the ground.

In the Victorian region
1000 MW of customer load lost during the fault has been restored
2690 Generation tripped

The AEMO instructed loadshed of 300 MW is being progressively restored.

Updates will be provided as additional information becomes available.

This Market Notice is issued in accordance with NER clause 4.8.3.

Manager NEM Real Time Operations
114617NON-CONFORMANCE13/02/2024 02:55:18 PM

NON-CONFORMANCE Region VIC1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 13/02/2024 14:50 to 13/02/2024 14:55
Amount: -25 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
114589RESERVE NOTICE13/02/2024 01:52:07 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:

[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations