117686SETTLEMENTS RESIDUE15/08/2024 06:05:21 PM

[EventId:202408151805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 August 2024 18:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 15 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 15 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117685SETTLEMENTS RESIDUE15/08/2024 06:00:50 PM

[EventId:202408151800_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 15 August 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 15 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 15 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1800 hrs on 15 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117677INTER-REGIONAL TRANSFER14/08/2024 04:22:12 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1620 hrs 14/08/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
117672INTER-REGIONAL TRANSFER14/08/2024 11:08:17 AM

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - CollectorWF-Marulan 4 330kV LINE - NSW region - 14/08/2024

At 1006 hrs 14/08/2024 there was a short notice outage of CollectorWF-Marulan 4 330kV LINE.

The following constraint set(s) invoked at 1000 hrs 14/08/2024
N-CTMN_4_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117669INTER-REGIONAL TRANSFER14/08/2024 08:05:49 AM

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

A planned outage of Collector - Marulan No 4 330kV Line in the NSW region was scheduled from 0800 hrs 14/08/2024 to 1700 hrs 02/09/2024.


The outage has been cancelled.

Constraint set(s) invoked: N-CTMN_4_WG_CLOSE


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
117662SETTLEMENTS RESIDUE13/08/2024 11:20:27 AM

[EventId:202408131120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 August 2024 11:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1120 hrs on 13 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.

Refer to market notice: 117661

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 13 August 2024.

This is an AEMO autogenerated Market Notice.
117661SETTLEMENTS RESIDUE13/08/2024 10:35:30 AM

[EventId:202408131035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 August 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 13 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 13 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117546INTER-REGIONAL TRANSFER04/08/2024 10:56:12 AM

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.

The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
117519SETTLEMENTS RESIDUE01/08/2024 07:45:19 AM

[EventId:202408010745_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 01 August 2024 07:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0745 hrs on 1 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 1 August 2024.

Refer to market notice: 117517

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 0745 hrs on 1 August 2024.

This is an AEMO autogenerated Market Notice.