NON-CONFORMANCE Region NSW1 Sunday, 4 February 2024
NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SEBSF1
Duration: 04/02/2024 11:05 to 04/02/2024 11:45
Amount: 35 MW
Constraint: NC-N_SEBSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 3 February 2024
NON-CONFORMANCE QLD1 Region Saturday, 3 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 03/02/2024 14:25 to 03/02/2024 14:35
Amount: -19 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 3 February 2024
NON-CONFORMANCE QLD1 Region Saturday, 3 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 03/02/2024 02:25 to 03/02/2024 02:45
Amount: -36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 21:40 to 01/02/2024 22:05
Amount: -24 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 18:30 to 01/02/2024 18:40
Amount: 50 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 31 January 2024
NON-CONFORMANCE QLD1 Region Wednesday, 31 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 31/01/2024 09:35 to 31/01/2024 09:45
Amount: 40 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0082222 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release