Market Notices

118257SETTLEMENTS RESIDUE12/09/2024 04:55:27 PM

[EventId:202409121655_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 16:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118256

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1655 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
118256SETTLEMENTS RESIDUE12/09/2024 03:05:26 PM

[EventId:202409121505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 12 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 12 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118248SETTLEMENTS RESIDUE12/09/2024 11:30:31 AM

[EventId:202409121130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118247

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
118247SETTLEMENTS RESIDUE12/09/2024 10:35:23 AM

[EventId:202409121035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 12 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 12 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118226GENERAL NOTICE10/09/2024 05:55:51 PM

Network Augmentation Commissioned - NSW Region - 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 10/09/2024

At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:

1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.

Manager NEM Real Time Operations
118199SETTLEMENTS RESIDUE08/09/2024 08:00:22 PM

[EventId:202409082000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 September 2024 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 8 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 September 2024.

Refer to market notice: 118188

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2000 hrs on 8 September 2024.

This is an AEMO autogenerated Market Notice.
118188SETTLEMENTS RESIDUE08/09/2024 06:16:24 PM

[EventId:202409081815_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 September 2024 18:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1815 hrs on 8 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118171POWER SYSTEM EVENTS06/09/2024 08:18:58 PM

Update - Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 06/09/2024

Refer AEMO Electricity Market Notice 118166

At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
118166POWER SYSTEM EVENTS06/09/2024 12:38:00 PM

Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/09/2024

At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations