Filter by category
Filter by Date
CHG0089536 | Production | Urgent NSW Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Urgent NSW Marketnet Router Replacement
Change Start Date & Time: 11/05/2024 10:00:27 AEST
Change End Date & Time: 11/05/2024 14:00:27 AEST
Outage Start Date & Time: 11/05/2024 10:00:26 AEST
Outage End Date & Time: 11/05/2024 12:00:26 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from NSW to QLD Datacenter.
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.
B2B VPN - No impact is expected.
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0089532 | Cancelled | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0089539 | Production | QLD Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: QLD Internet Router Refresh
Change Start Date & Time: 25/05/2024 09:00:08 AEST
Change End Date & Time: 25/05/2024 14:00:08 AEST
Outage Start Date & Time: 25/05/2024 09:30:21 AEST
Outage End Date & Time: 25/05/2024 13:00:21 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: No impact is expected as GASHUB is currently operating out of NOR Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202405082030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 8 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Refer to market notice: 116542
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 8 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405081530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 8 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 8 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202405080830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 08:30
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 8 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Refer to market notice: 116521
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0830 hrs on 8 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405080635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 06:35
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 8 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0635 hrs on 8 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202405071930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 May 2024 19:30
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 7 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.
Refer to market notice: 116512
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 7 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405071715_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 May 2024 17:15
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 7 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1715 hrs on 7 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.