Market Notices

113677RESERVE NOTICE23/01/2024 07:49:57 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1700 hrs 26/01/2024 to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 798 MW.
The minimum capacity reserve available is 651 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113676RESERVE NOTICE23/01/2024 07:40:09 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1700 hrs 26/01/2024 to 1900 hrs 26/01/2024.
The forecast capacity reserve requirement is 1126 MW.
The minimum capacity reserve available is 1020 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
113675RESERVE NOTICE23/01/2024 07:38:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113669 has been updated at 1930 hrs 23/01/2024 to the following:

[1.] From 1430 hrs 25/01/2024 to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1366 MW.
The minimum capacity reserve available is 804 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113669RESERVE NOTICE23/01/2024 03:42:55 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113663 has been updated at 1400 hrs 23/01/2024 to the following:

From 1400 hrs to 2100 hrs 25/01/2024.
The forecast capacity reserve requirement is 1316 MW.
The minimum capacity reserve available is 617 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113668RESERVE NOTICE23/01/2024 03:41:31 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113664 is cancelled at 1400 hrs 23/01/2024.

AEMO Operations
113666RESERVE NOTICE23/01/2024 12:54:38 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113665 is cancelled at 1200 hrs 23/01/2024.

AEMO Operations
113665RESERVE NOTICE23/01/2024 11:56:23 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 2030 hrs 29/01/2024.
The forecast capacity reserve requirement is 520 MW.
The minimum capacity reserve available is 495 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113664RESERVE NOTICE23/01/2024 11:54:42 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113661 has been updated at 1100 hrs 23/01/2024 to the following:

From 1730 hrs to 2000 hrs 25/01/2024.
The forecast capacity reserve requirement is 738 MW.
The minimum capacity reserve available is 725 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113663RESERVE NOTICE23/01/2024 11:53:42 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113658 has been updated at 1100 hrs 23/01/2024 to the following:

From 1430 hrs 25/01/2024 to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1362 MW.
The minimum capacity reserve available is 622 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations