Filter by category
Filter by Date
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 1030 hrs 28/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/05/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/05/2024
Refer Market Notice 116814
The AEMO Intervention Event and all associated directions are cancelled from 0935 hrs 27/05/2024
Manager NEM Real Time Operations
CHG0089539 | Completed | Production | QLD Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: QLD Internet Router Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Direction - SA region 26/05/2024
Direction - SA region 26/05/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1535 hrs on 26/05/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116808
The synchronous generating units currently expected to be synchronised in SA from 1030 hrs 27/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1530 hrs 26/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 25/05/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 25/05/2024
Refer Market Notice 116806
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs 26/05/2024
Manager NEM Real Time Operations
CHG0087769 | Completed | Production | Production MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Production MSATS Lifecycle Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 27/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Direction - SA region 25/05/2024
Direction - SA region 25/05/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 25/05/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations