STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113754 is cancelled at 0500 hrs 26/01/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113750 has been updated at 2200 hrs 25/01/24 to the following:
From 1800 hrs 27/01/2024 to 1900 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 693 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113740 has been updated at 1600 hrs to the following:
From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 731 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113732 has been updated at 1300 hrs to the following:
From 1700 hrs to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 766 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113730 has been updated at 1100 hrs to the following:
1. From 1730 hrs to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 743 MW.
The minimum capacity reserve available is 708 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
NEM Local Temperature Alerts for NSW, QLD, SA from 25 Jan 2024 to 29 Jan 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
NSW
Sydney Observatory Hill (39+ Deg C): 26th Jan
QLD
Dalby Ap (37+ Deg C): 25th Jan, 26th Jan, 27th Jan
SA
Port Augusta Ap (39+ Deg C): 29th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113722 has been updated at 1000 hrs to the following:
1. From 1730 hrs to 1830 hrs 27/01/2024.
The forecast capacity reserve requirement is 740 MW.
The minimum capacity reserve available is 735 MW.
2. From 1900 hrs to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 734 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113711 is cancelled at 0800 hrs 25/01/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113714 has been updated at 0430 hrs to the following:
[1.] From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 573 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations