Market Notices

120566PRICES UNCHANGED17/11/2024 04:17:58 PM

[EventId:202411171605_confirmed] Prices for interval 17-Nov-2024 16:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:05.

In accordance with Market Notice 120560 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120565PRICES UNCHANGED17/11/2024 04:15:24 PM

[EventId:202411171600_confirmed] Prices for interval 17-Nov-2024 16:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:00.

In accordance with Market Notice 120559 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120564PRICES UNCHANGED17/11/2024 04:16:48 PM

[EventId:202411171550_confirmed] Prices for interval 17-Nov-2024 15:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 15:50.

In accordance with Market Notice 120557 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120554MARKET INTERVENTION17/11/2024 03:59:45 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 120529

The MINTARO MINTARO GAS direction is now expected to stay in place until 1830 hrs 18/11/2024.

The direction update is issued at 1600 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120553MARKET INTERVENTION17/11/2024 03:57:41 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120528

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/11/2024.

The direction update is issued at 1600 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120530MARKET INTERVENTION16/11/2024 05:00:04 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120527

Direction is cancelled from: 1700 hrs 16/11/2024

Manager NEM Real Time Operations
     
120529MARKET INTERVENTION16/11/2024 03:59:06 PM

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 16/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0100 hrs 17/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 18/11/2024.

Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120528MARKET INTERVENTION16/11/2024 03:56:33 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120500

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/11/2024.

The direction update is issued at 1600 hrs 16/11/2024.

Manager NEM Real Time Operations
     
120527MARKET INTERVENTION16/11/2024 02:39:52 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120498

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 16/11/2024.

The direction update is issued at 1440 hrs 16/11/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm