[EventId:202501021300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 January 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 2 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 January 2025.
Refer to market notice: 122714
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 2 January 2025.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 02/01/2025 10:56 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501021030_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 January 2025 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 2 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1030 hrs on 2 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501021030_review] Prices for interval 02-Jan-2025 10:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 2 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501021025_review] Prices for interval 02-Jan-2025 10:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 2 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501021020_review] Prices for interval 02-Jan-2025 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 2 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501021015_review] Prices for interval 02-Jan-2025 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 2 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501021010_review] Prices for interval 02-Jan-2025 10:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 2 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Jan-2025 10:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501021000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 January 2025 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 2 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 January 2025.
Refer to market notice: 122698
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 2 January 2025.