Market Notices

120099MINIMUM SYSTEM LOAD07/11/2024 03:11:35 PM

Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 07/11/2024.

Refer to Market Notice 119996 for Forecast MSL1.

AEMO Operations
     
120098MARKET INTERVENTION07/11/2024 02:22:00 PM

Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2300 hrs 07/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 07/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
120097MARKET INTERVENTION07/11/2024 02:20:36 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120014

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 07/11/2024.

The direction update is issued at 1420 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120096SETTLEMENTS RESIDUE07/11/2024 02:05:43 PM

[EventId:202411071405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 7 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 7 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120095SETTLEMENTS RESIDUE07/11/2024 01:30:26 PM

[EventId:202411071330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 November 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 7 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Refer to market notice: 120076

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 7 November 2024.

This is an AEMO autogenerated Market Notice.
     
120077MARKET INTERVENTION07/11/2024 12:09:50 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120013

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 07/11/2024.

The direction update is issued at 1208 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120076SETTLEMENTS RESIDUE07/11/2024 12:04:04 PM

[EventId:202411071200_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 November 2024 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 7 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1200 hrs on 7 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120031MARKET INTERVENTION06/11/2024 05:57:50 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875

Direction is cancelled from: 1800 hrs 06/11/2024

Manager NEM Real Time Operations
     
120019MARKET INTERVENTION06/11/2024 05:07:43 PM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1655 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1700 hrs 06/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 06/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm