Market Notices

120123SETTLEMENTS RESIDUE07/11/2024 09:30:57 PM

[EventId:202411072130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 November 2024 21:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2130 hrs on 7 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Refer to market notice: 120096

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2130 hrs on 7 November 2024.

This is an AEMO autogenerated Market Notice.
     
120100NON-CONFORMANCE07/11/2024 03:05:12 PM

NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 07/11/2024 14:35 to 07/11/2024 15:05
Amount: -32 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120096SETTLEMENTS RESIDUE07/11/2024 02:05:43 PM

[EventId:202411071405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 7 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 7 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120095SETTLEMENTS RESIDUE07/11/2024 01:30:26 PM

[EventId:202411071330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 November 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 7 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 November 2024.

Refer to market notice: 120076

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 7 November 2024.

This is an AEMO autogenerated Market Notice.
     
120086PRICES SUBJECT TO REVIEW07/11/2024 01:01:55 PM

[EventId:202411071305_review] Prices for interval 07-Nov-2024 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 7 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120085PRICES SUBJECT TO REVIEW07/11/2024 12:56:01 PM

[EventId:202411071300_review] Prices for interval 07-Nov-2024 13:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 7 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 13:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120082PRICES SUBJECT TO REVIEW07/11/2024 12:50:19 PM

[EventId:202411071255_review] Prices for interval 07-Nov-2024 12:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 7 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 12:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120081PRICES SUBJECT TO REVIEW07/11/2024 12:45:25 PM

[EventId:202411071250_review] Prices for interval 07-Nov-2024 12:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1245 hrs on 7 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 12:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120079PRICES SUBJECT TO REVIEW07/11/2024 12:40:27 PM

[EventId:202411071245_review] Prices for interval 07-Nov-2024 12:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1240 hrs on 7 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 12:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm