Market Notices

119966MARKET INTERVENTION06/11/2024 01:19:39 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 07/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
119963GENERAL NOTICE06/11/2024 11:27:15 AM

Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119961

This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.

The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Mya San
AEMO Operations
     
119961GENERAL NOTICE06/11/2024 10:03:46 AM

Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119901

The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.

The test is for flows in both directions up to 50 MW.

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Terry Liu
AEMO Operations
     
119934MARKET INTERVENTION06/11/2024 01:08:35 AM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119931

The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0230 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.

The direction update is issued at 0105 hrs 06/11/2024.

Manager NEM Real Time Operations
     
119931MARKET INTERVENTION05/11/2024 09:54:45 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119929

The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0200 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.

The direction update is issued at 2155 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119929MARKET INTERVENTION05/11/2024 06:55:47 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119924

The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 2330 hrs 05/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.

The direction update is issued at 1855 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119924MARKET INTERVENTION05/11/2024 04:14:12 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119875

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 06/11/2024.

The direction update is issued at 1610 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119923MARKET INTERVENTION05/11/2024 04:12:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119875

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 06/11/2024.

The direction update is issued at 1610 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119922MARKET INTERVENTION05/11/2024 03:31:29 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119875

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 06/11/2024.

The direction update is issued at 1530 hrs 05/11/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm