Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Sunday, 29 September 2024
NON-CONFORMANCE QLD1 Region Sunday, 29 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 29/09/2024 08:35 to 29/09/2024 09:05
Amount: -38 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line- NSW region - 29/09/2024
Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line - NSW region - 29/09/2024
At 0313 hrs 29/09/2024 there was an unplanned outage of Stockdill - Upper Tumut 1 330 kV line.
The following constraint set invoked at 0320 hrs 29/09/2024
N-SDUT_1
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202409281420_review] Prices for interval 28-Sep-2024 14:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409281415_review] Prices for interval 28-Sep-2024 14:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409281410_review] Prices for interval 28-Sep-2024 14:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409281405_review] Prices for interval 28-Sep-2024 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409281400_review] Prices for interval 28-Sep-2024 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409281355_review] Prices for interval 28-Sep-2024 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 28 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 28-Sep-2024 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409261605_review] Prices for interval 26-Sep-2024 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 26 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Sep-2024 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.