STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113804 is cancelled at 2000 hrs 26/01/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1700 hrs 27/01/2024 to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 568 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1300 hrs 28/01/2024 to 1430 hrs 28/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 646 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113768 is cancelled at 1545 hrs 26/01/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113766 has been updated at 1420 hrs to the following:
[1.] From 1730 hrs 27/01/2024 to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 606 MW.
The minimum capacity reserve available is 336 MW.
[2.] From 2100 hrs 27/01/2024 to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 610 MW.
The minimum capacity reserve available is 546 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1700 hrs 27/01/2024 to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 610 MW.
The minimum capacity reserve available is 344 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113754 is cancelled at 0500 hrs 26/01/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113750 has been updated at 2200 hrs 25/01/24 to the following:
From 1800 hrs 27/01/2024 to 1900 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 693 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113740 has been updated at 1600 hrs to the following:
From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 731 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations