NON-CONFORMANCE Region NSW1 Tuesday, 5 December 2023
NON-CONFORMANCE NSW1 Region Tuesday, 5 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NEWENSF1
Duration: 05/12/2023 12:25 to 05/12/2023 12:45
Amount: 25 MW
Constraint: NC-N_NEWENSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 4 December 2023
NON-CONFORMANCE QLD1 Region Monday, 4 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-1
Duration: 04/12/2023 09:20 to 04/12/2023 09:25
Amount: -31 MW
Constraint: NC-Q_STAN-1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023
Cancellation of Actual (LOR1) condition in the QLD region - 02/12/2023
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.111943 is cancelled at 1945 hrs 02/12/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 02/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1820 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1299 MW
The minimum capacity reserve available is 1167 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 2 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 2 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 02/12/2023 11:40 to 02/12/2023 11:50
Amount: -16 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations