NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024
NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 13/02/2024 11:10 to 13/02/2024 11:25
Amount: 10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024
NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WATERLWF
Duration: 13/02/2024 08:15 to 13/02/2024 08:50
Amount: 43 MW
Constraint: NC-S_WATERLWF
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 13 February 2024
NON-CONFORMANCE NSW1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP1
Duration: 13/02/2024 04:55 to 13/02/2024 05:00
Amount: 21 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 12 February 2024
NON-CONFORMANCE QLD1 Region Monday, 12 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 12/02/2024 20:15 to 12/02/2024 20:25
Amount: -63 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 12 February 2024
NON-CONFORMANCE VIC1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: BALBG1, BALBL1
Aggregate Dispatch Group: BALBESS_ADG1
Duration: 12/02/2024 13:30 to 12/02/2024 13:40
Amount: 23 MW
Constraint: NC-V_BALBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 50 MW
Constraint: NC-N_RESS2_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 10 February 2024
NON-CONFORMANCE VIC1 Region Saturday, 10 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNSF1
Duration: 10/02/2024 10:40 to 10/02/2024 10:55
Amount: 25 MW
Constraint: NC-V_GANNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .