Filter by category
Filter by Date
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120433
The JLB01 JEERALANG B PO direction is now expected to stay in place until 2100 hrs 14/11/2024.
The direction update is issued at 1715 hrs 14/11/2024.
Manager NEM Real Time Operations
[EventId:202411141705_review] Prices for interval 14-Nov-2024 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 14 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Nov-2024 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - AEMO Intervention Event - VIC region 14/11/2024
Update - AEMO Intervention Event - VIC region 14/11/2024
Refer to Market Notice 120420
The AEMO Intervention Event and all associated directions are NOT cancelled from 1700 hrs on 14/11/2024.
The AEMO Intervention event and all associated directions are continuing.
Manager NEM Real Time Operations
[EventId:202411141645_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 November 2024 16:45
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 14 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 November 2024.
Refer to market notice: 120437
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1645 hrs on 14 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411141630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 November 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 14 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 14 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2
Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2
Refer AEMO Electricity Participant Notice 120428
The MURR2-3 MURRAY2 direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2
Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2
Refer AEMO Electricity Participant Notice 120427
The MURR2-2 MURRAY2 direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120426
The JLB02 JEERALANG B PO direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO
Refer AEMO Electricity Participant Notice 120425
The JLB01 JEERALANG B PO direction is now expected to stay in place until 1700 hrs 14/11/2024.
The direction update is issued at 1620 hrs 14/11/2024.
Manager NEM Real Time Operations