125520RECLASSIFY CONTINGENCY11/03/2025 11:03:51 AM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 11/03/2025 11:03 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125517POWER SYSTEM EVENTS11/03/2025 10:05:23 AM

Non-credible contingency event - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/03/2025

At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.

AEMO did not instruct load shedding.

Approximately 3 MW of electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
125515RECLASSIFY CONTINGENCY11/03/2025 09:14:01 AM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 11/03/2025 09:13

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125501

Auto-generated on behalf of Manager NEM Real Time Operations
     
125507PRICES SUBJECT TO REVIEW11/03/2025 08:15:17 AM

[EventId:202503110820_review] Prices for interval 11-Mar-2025 08:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125506PRICES SUBJECT TO REVIEW11/03/2025 08:10:17 AM

[EventId:202503110815_review] Prices for interval 11-Mar-2025 08:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0810 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125505PRICES SUBJECT TO REVIEW11/03/2025 08:05:18 AM

[EventId:202503110810_review] Prices for interval 11-Mar-2025 08:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0805 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125504PRICES SUBJECT TO REVIEW11/03/2025 08:00:21 AM

[EventId:202503110805_review] Prices for interval 11-Mar-2025 08:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125503PRICES SUBJECT TO REVIEW11/03/2025 07:55:17 AM

[EventId:202503110800_review] Prices for interval 11-Mar-2025 08:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0755 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125502PRICES SUBJECT TO REVIEW11/03/2025 07:50:25 AM

[EventId:202503110755_review] Prices for interval 11-Mar-2025 07:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0750 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 07:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     