[EventId:202410241440_confirmed] Prices for interval 24-Oct-2024 14:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 24 October 2024
PRICES ARE NOW CONFIRMED for trading interval 24-Oct-2024 14:40.
In accordance with Market Notice 119320 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410241445_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 October 2024 14:45
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 24 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1445 hrs on 24 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410241430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 October 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 24 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Refer to market notice: 119305
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 24 October 2024.
This is an AEMO autogenerated Market Notice.
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119265
Direction is cancelled from: 1830 hrs 24/10/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - VIC region 24/10/2024
Cancellation - AEMO Intervention Event - VIC region 24/10/2024
Refer to Market Notice 119272
The AEMO Intervention Event and all associated directions are cancelled from 1535 hrs on 24/10/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2
Refer to Market Notice 119293
Direction is cancelled from: 1535 hrs 24/10/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Refer to Market Notice 119292
Direction is cancelled from: 1535 hrs 24/10/2024
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/10/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1800 hrs to 1900 hrs 28/10/2024.
The forecast capacity reserve requirement is 607 MW.
The minimum capacity reserve available is 517 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202410241310_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 October 2024 13:10
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 24 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1310 hrs on 24 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.