112074RECLASSIFY CONTINGENCY08/12/2023 10:50:21 AM

Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action to maintain power system security at 1050 hrs 08/12/2023.
Constraint set invoked: I-VS_250

Duration: 1050 hrs 08/12/2023. until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
112065GENERAL NOTICE08/12/2023 10:52:48 AM

NEM Local Temperature Alerts for NSW, SA, VIC from 08 Dec 2023 to 12 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Yass (39+ Deg C): 9th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112059RECLASSIFY CONTINGENCY08/12/2023 09:52:08 AM

Reclassification of a Non-Credible Contingency Event: Loss of Sheffield 220 kV switchyard (all 220 kV buses) in Tas due to planned work

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to planned work.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region:TAS

Plant: Sheffield 220 kV switchyard (all 220 kV buses)

Duration: 08/12/2023 : 1000 hrs until further notice

Constraint set(s) invoked: T:SH_220_N-2

Manager NEM Real Time Operations
112058MARKET SYSTEMS08/12/2023 07:05:32 AM

CHG0082118 | Completed | Production | Planned System Maintenance activity.

Change Number: CHG0082118
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Network Outage Scheduler
Change Title: Planned System Maintenance activity.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112056RECLASSIFY CONTINGENCY08/12/2023 11:09:48 AM

Reclassification of a Non-Credible Contingency Event: South East - Tailem Bend No.1 and No.2 275 kV lines 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: South East - Tailem Bend No.1 and No.2 275 kV lines

Duration: 08/12/2023 11:10 hrs until further notice

Constraint set(s) invoked: S-SETB_N-2

Manager NEM Real Time Operations
112055RECLASSIFY CONTINGENCY08/12/2023 11:07:29 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 08/12/2023 10:50 hrs until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
112054RECLASSIFY CONTINGENCY08/12/2023 11:08:47 AM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 08/12/2023 10:50 hrs until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
112053RECLASSIFY CONTINGENCY08/12/2023 04:19:37 AM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 08/12/2023 04:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 112051

Auto-generated on behalf of Manager NEM Real Time Operations
112051RECLASSIFY CONTINGENCY08/12/2023 02:15:46 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 08/12/2023 02:15 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations