Market Notices

117571RECLASSIFY CONTINGENCY06/08/2024 02:54:13 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 06/08/2024 14:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117567

Auto-generated on behalf of Manager NEM Real Time Operations
117567RECLASSIFY CONTINGENCY06/08/2024 12:52:37 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 06/08/2024 12:52 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
117565RESERVE NOTICE05/08/2024 09:47:16 PM

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117564 is cancelled at 2145 hrs 05/08/2024.

Manager NEM Real Time Operations
117564RESERVE NOTICE05/08/2024 09:25:40 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2130 hrs.

The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.

Manager NEM Real Time Operations
117563RESERVE NOTICE05/08/2024 08:44:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.

The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW

Manager NEM Real Time Operations
117560PRICES UNCHANGED05/08/2024 05:06:44 PM

[EventId:202408051640_confirmed] Prices for interval 05-Aug-2024 16:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:40.

In accordance with Market Notice 117549 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117559PRICES UNCHANGED05/08/2024 05:04:37 PM

[EventId:202408051700_confirmed] Prices for interval 05-Aug-2024 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 17:00.

In accordance with Market Notice 117553 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117558PRICES UNCHANGED05/08/2024 05:08:01 PM

[EventId:202408051655_confirmed] Prices for interval 05-Aug-2024 16:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:55.

In accordance with Market Notice 117552 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117557PRICES UNCHANGED05/08/2024 05:02:48 PM

[EventId:202408051650_confirmed] Prices for interval 05-Aug-2024 16:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:50.

In accordance with Market Notice 117551 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm