Market Notices

114429INTER-REGIONAL TRANSFER07/02/2024 07:06:39 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114407INTER-REGIONAL TRANSFER06/02/2024 09:12:48 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC

The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113958RESERVE NOTICE29/01/2024 09:17:19 AM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:

1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.

2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.

AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.

AEMO Operations
113860POWER SYSTEM EVENTS27/01/2024 02:49:35 PM

Cancellation - Non-credible contingency event - QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Cancellation - Non-credible contingency event - QLD region - 27/01/2024

Refer AEMO Electricity Market Notice 113825

At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.

AEMO has received further information and now determines this was not a non-credible contingency event.

Manager NEM Real Time Operations
113825POWER SYSTEM EVENTS27/01/2024 01:57:16 AM

Non-credible contingency event - QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/01/2024

At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
113662POWER SYSTEM EVENTS23/01/2024 11:31:54 AM

Update - Non-credible contingency event - QLD region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 23/01/2024

Refer AEMO Electricity Market Notice 113659

At 1122 hrs the H35 Strathmore No2 275 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

Nebo - Strathmore 878 275 kV line to remain out of service.

See Network Outage Scheduler (NOS) for further details.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
113659POWER SYSTEM EVENTS23/01/2024 10:20:24 AM

Non-credible contingency event - QLD region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 23/01/2024

At 0957 hrs the Strathmore No 2 275 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS

Manager NEM Real Time Operations
113654INTER-REGIONAL TRANSFER23/01/2024 03:30:39 AM

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.

The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113416INTER-REGIONAL TRANSFER18/01/2024 03:14:09 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 1510 hrs 18/01/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm