Filter by category
Filter by Date
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024
Refer Market Notice 117076
The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs 20/06/2024
Manager NEM Real Time Operations
Direction - SA region 19/06/2024
Direction - SA region 19/06/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1650 hrs on 19/06/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117061
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 19/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 17 June 2024
NON-CONFORMANCE QLD1 Region Monday, 17 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 17/06/2024 04:30 to 17/06/2024 05:25
Amount: -51 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Refer Market Notice 116996
AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.
Manager NEM Real Time Operations
[EventId:202406141420_confirmed] Prices for interval 14-Jun-2024 14:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 14 June 2024
PRICES ARE NOW CONFIRMED for trading interval 14-Jun-2024 14:20.
In accordance with Market Notice 116992 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406141440_confirmed] Prices for interval 14-Jun-2024 14:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 14 June 2024
PRICES ARE NOW CONFIRMED for trading interval 14-Jun-2024 14:40.
In accordance with Market Notice 116998 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406141435_confirmed] Prices for interval 14-Jun-2024 14:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 14 June 2024
PRICES ARE NOW CONFIRMED for trading interval 14-Jun-2024 14:35.
In accordance with Market Notice 116995 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.