Market Notices

119460RESERVE NOTICE27/10/2024 12:22:21 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs to 1830 hrs 29/10/2024.
The forecast capacity reserve requirement is 836 MW.
The minimum capacity reserve available is 824 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119459MARKET INTERVENTION26/10/2024 08:39:40 PM

Cancellation - MSL1- VIC Region on 27/10/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region on 27/10/2024.

The Forecast MSL1 condition in the VIC region advised in AEMO Electricity Market Notice No. 119412 is cancelled at 2030 hrs 26/10/2024.


Manager NEM Real Time Operations
     
119444MARKET INTERVENTION26/10/2024 04:55:22 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119416

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 28/10/2024.

The direction update is issued at 1700 hrs 26/10/2024.

Manager NEM Real Time Operations
     
119443MARKET INTERVENTION26/10/2024 04:56:36 PM

Direction - SA region AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119414


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 26/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0700 hrs 27/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 28/10/2024 .

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119442MARKET INTERVENTION26/10/2024 05:25:42 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119440

Direction is cancelled from: 1730 hrs 26/10/2024

Manager NEM Real Time Operations
     
119440MARKET INTERVENTION26/10/2024 01:54:52 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119421

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 26/10/2024.

The direction update is issued at 1400 hrs 26/10/2024.

Manager NEM Real Time Operations
     
119421MARKET INTERVENTION25/10/2024 07:55:26 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119415

The updated required actions: Synchronise and follow dispatch targets at 2200 hrs 25/10/2024

The direction update is issued at 1955 hrs 25/10/2024.

Manager NEM Real Time Operations
     
119416MARKET INTERVENTION25/10/2024 04:52:18 PM

Direction - SA AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 119414


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 25/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 25/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 27/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119415MARKET INTERVENTION25/10/2024 04:55:10 PM

Direction - SA AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119414


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 25/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0030 hrs 26/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1630 hrs 26/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm