124104PRICES SUBJECT TO REVIEW04/02/2025 03:29:00 PM

[EventId:202502041530_review] Prices for interval 04-Feb-2025 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124103PRICES SUBJECT TO REVIEW04/02/2025 03:20:34 PM

[EventId:202502041525_review] Prices for interval 04-Feb-2025 15:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124101PRICES SUBJECT TO REVIEW04/02/2025 03:17:14 PM

[EventId:202502041520_review] Prices for interval 04-Feb-2025 15:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1515 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124099PRICES SUBJECT TO REVIEW04/02/2025 03:31:50 PM

[EventId:202502041515_review] Prices for interval 04-Feb-2025 15:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1510 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 15:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124098SETTLEMENTS RESIDUE04/02/2025 03:07:51 PM

[EventId:202502041500_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 04 February 2025 15:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 4 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Refer to market notice: 124084

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1500 hrs on 4 February 2025.

This is an AEMO autogenerated Market Notice.
     
124090RESERVE NOTICE04/02/2025 03:14:01 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1630 hrs 04/02/2025 to 1830 hrs 04/02/2025.
The forecast capacity reserve requirement is 993 MW.
The minimum capacity reserve available is 768 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
124084SETTLEMENTS RESIDUE04/02/2025 02:42:10 PM

[EventId:202502041335_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 04 February 2025 13:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 4 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 4 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1335 hrs on 4 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124076PRICES SUBJECT TO REVIEW04/02/2025 02:05:33 PM

[EventId:202502041330_review] Prices for interval 04-Feb-2025 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124075PRICES SUBJECT TO REVIEW04/02/2025 01:47:11 PM

[EventId:202502041325_review] Prices for interval 04-Feb-2025 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm