123214MARKET INTERVENTION14/01/2025 04:04:54 PM

Direction - SA region 14/01/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 14/01/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 14/01/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
123213MARKET INTERVENTION14/01/2025 03:29:29 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123201

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 14/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123206RESERVE NOTICE14/01/2025 01:49:41 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1570 MW.

Manager NEM Real Time Operations
     
123202SETTLEMENTS RESIDUE14/01/2025 01:00:24 PM

[EventId:202501141300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 January 2025 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 14 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.

Refer to market notice: 123198

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 14 January 2025.

This is an AEMO autogenerated Market Notice.
     
123201MARKET INTERVENTION14/01/2025 01:09:01 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 15/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123198SETTLEMENTS RESIDUE14/01/2025 11:35:25 AM

[EventId:202501141135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 January 2025 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 14 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 14 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123184SETTLEMENTS RESIDUE13/01/2025 07:45:27 PM

[EventId:202501131945_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 January 2025 19:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 13 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.

Refer to market notice: 123173

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1945 hrs on 13 January 2025.

This is an AEMO autogenerated Market Notice.
     
123173SETTLEMENTS RESIDUE13/01/2025 05:06:01 PM

[EventId:202501131705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 January 2025 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 13 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 13 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123167RESERVE NOTICE13/01/2025 04:33:47 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123157 has been updated at 1630 hrs to the following:


[1.] From 1630 hrs 13/01/2025 to 1700 hrs 13/01/2025.
The forecast capacity reserve requirement is 1372 MW.
The minimum capacity reserve available is 1061 MW.

[2.] From 1900 hrs 13/01/2025 to 2000 hrs 13/01/2025.
The forecast capacity reserve requirement is 1603 MW.
The minimum capacity reserve available is 1214 MW.


Manager NEM Real Time Operations
     