119072MARKET INTERVENTION19/10/2024 04:34:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119025

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/10/2024.

The direction update is issued at 1630 hrs 19/10/2024.

Manager NEM Real Time Operations
     
119071MARKET INTERVENTION19/10/2024 04:32:59 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119026

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/10/2024.

The direction update is issued at 1630 hrs 19/10/2024.

Manager NEM Real Time Operations
     
119026MARKET INTERVENTION18/10/2024 04:00:48 PM

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 18/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1100 hrs 19/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119025MARKET INTERVENTION18/10/2024 03:59:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118991

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/10/2024.

The direction update is issued at 1600 hrs 18/10/2024.

Manager NEM Real Time Operations
     
119024MARKET INTERVENTION18/10/2024 03:56:24 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 118990

The MINTARO MINTARO GAS direction is now expected to stay in place until 1100 hrs 19/10/2024.

The direction update is issued at 1600 hrs 18/10/2024.

Manager NEM Real Time Operations
     
118991MARKET INTERVENTION17/10/2024 03:58:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118986

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/10/2024.

The direction update is issued at 1600 hrs 17/10/2024.

Manager NEM Real Time Operations
     
118990MARKET INTERVENTION17/10/2024 03:59:58 PM

Direction - SA region - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region - Synergen Power Pty Limited - MINTARO MINTARO GAS

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 17/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 2300 hrs 17/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 19/10/2024

Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118986MARKET INTERVENTION17/10/2024 12:33:07 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118968

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/10/2024.

The direction update is issued at 1230 hrs 17/10/2024.

Manager NEM Real Time Operations
     
118985MARKET INTERVENTION17/10/2024 12:31:52 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 118984

Direction is cancelled from: 1230 hrs 17/10/2024