112483RESERVE NOTICE18/12/2023 05:03:52 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112471 has been updated at 0500 hrs 18/12/2023 to the following:

From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1071 MW.
The minimum capacity reserve available is 42 MW.

AEMO is seeking a market response.

AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.

Manager NEM RTO
112482MARKET INTERVENTION18/12/2023 05:05:06 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 19/12/2023 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112471RESERVE NOTICE17/12/2023 03:22:25 PM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112427 has been updated at 1515 hrs 17/12/2023 to the following:

From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1346 MW.
The minimum capacity reserve available is 205 MW.

AEMO is seeking a market response.

AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.

Manager NEM RTO
112470MARKET INTERVENTION17/12/2023 02:40:23 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 18/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 17/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112469MARKET INTERVENTION17/12/2023 05:02:10 PM

Direction - SA region 17/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 17/12/2023

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1700 hrs on 17/12/2023.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
112467MARKET INTERVENTION17/12/2023 02:35:23 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1700 hrs 18/12/2023 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 17/12/2023, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112452MARKET INTERVENTION17/12/2023 05:05:07 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/12/2023

Refer Market Notice 112423

The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs 17/12/2023

Manager NEM Real Time Operations
112449MARKET INTERVENTION17/12/2023 12:51:49 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 18/12/2023 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
112427RESERVE NOTICE16/12/2023 03:34:00 PM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112392 has been updated at 1530 hrs 16/12/2023 to the following:

From 1330 hrs to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 128 MW.

AEMO is seeking a market response.

AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.

Manager NEM RTO