Filter by category
Filter by Date
CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202401291820_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 January 2024 18:20
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 29 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 January 2024.
Refer to market notice: 113992
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1820 hrs on 29 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401291755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 January 2024 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 29 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2024.
Refer to market notice: 113985
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 29 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401291755_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 January 2024 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 29 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1755 hrs on 29 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202401291630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 January 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 29 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 29 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Monday, 29 January 2024
NON-CONFORMANCE NSW1 Region Monday, 29 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1254 MW.
The minimum capacity reserve available is 1187 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1430 hrs to 2200 hrs 05/02/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113912 has been updated at 1400 hrs 29/01/2024 to the following:
From 1700 hrs to 2130 hrs 04/02/2024.
The forecast capacity reserve requirement is 1489 MW.
The minimum capacity reserve available is 1108 MW.