Market Notices

113382SETTLEMENTS RESIDUE17/01/2024 07:06:32 PM

[EventId:202401171905_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 17 January 2024 19:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 17 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 17 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1905 hrs on 17 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113381PRICES SUBJECT TO REVIEW17/01/2024 07:05:16 PM

[EventId:202401171910_review] Prices for interval 17-Jan-2024 19:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113380PRICES SUBJECT TO REVIEW17/01/2024 07:00:15 PM

[EventId:202401171905_review] Prices for interval 17-Jan-2024 19:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113379PRICES SUBJECT TO REVIEW17/01/2024 06:55:19 PM

[EventId:202401171900_review] Prices for interval 17-Jan-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113378PRICES SUBJECT TO REVIEW17/01/2024 06:50:18 PM

[EventId:202401171855_review] Prices for interval 17-Jan-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113377PRICES SUBJECT TO REVIEW17/01/2024 06:45:11 PM

[EventId:202401171850_review] Prices for interval 17-Jan-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113376PRICES SUBJECT TO REVIEW17/01/2024 06:40:19 PM

[EventId:202401171845_review] Prices for interval 17-Jan-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113357NON-CONFORMANCE17/01/2024 12:15:14 PM

NON-CONFORMANCE Region NSW1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 17/01/2024 12:00 to 17/01/2024 12:15
Amount: 21 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
113354NON-CONFORMANCE17/01/2024 10:20:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/01/2024 10:05 to 17/01/2024 10:20
Amount: 46 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
X