116885PRICES SUBJECT TO REVIEW04/06/2024 06:30:17 PM

[EventId:202406041835_review] Prices for interval 04-Jun-2024 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116884MARKET SYSTEMS04/06/2024 02:28:55 PM

CHG0089854 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0089854
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 11/06/2024 09:00:00 AEST
Change End Date & Time: 11/06/2024 22:00:00 AEST
Outage Start Date & Time: 11/06/2024 18:30:00 AEST
Outage End Date & Time: 11/06/2024 21:00:00 AEST

Environment: Production

Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
116882RESERVE NOTICE03/06/2024 05:49:43 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116881 for the 04/06/2024 is cancelled at 1745 hrs 03/06/2024.

Manager NEM Real Time Operations
116881RESERVE NOTICE03/06/2024 05:20:08 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 04/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1700 hrs 04/06/2024 to 1730 hrs 04/06/2024.
The forecast capacity reserve requirement is 448 MW.
The minimum capacity reserve available is 411 MW.

Manager NEM Real Time Operations
116880MARKET SYSTEMS03/06/2024 03:44:54 PM

CHG0090097 | Completed | Pre-Production | Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.

Change Number: CHG0090097
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: Declared Wholesale Gas Market (DWGM)

Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
116879GENERAL NOTICE03/06/2024 10:49:16 AM

Fast Frequency Response Market - Increase in R1 and L1 FCAS dispatch caps from 11th June 2024

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Tuesday 11th June AEMO will:

Increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 325 MW to 350 MW

Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 200 MW to 225 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
116874GENERAL NOTICE01/06/2024 08:31:10 PM

Network Augmentation Commissioned - QLD Region - 01/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 01/06/2024

H90 Tully South 275 kV Switching Station has been cut into the existing Ross - Woree No.8905 275 kV line to form the following circuits:

H13 Ross - H90 Tully South No.8905/1 275 kV line
H90 Tully South - H39 Woree No.8905/2 275 kV line

Manager NEM Real Time Operations