[EventId:202410280305_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 28 October 2024 03:05
Issued by Australian Energy Market Operator Ltd at 0305 hrs on 28 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 28 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0305 hrs on 28 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119493 has been updated at 2230 hrs to the following:
[1.] From 2000 hrs 28/10/2024 to 2030 hrs 28/10/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 903 MW.
Manager NEM Real Time Operations
[EventId:202410271400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 October 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 27 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 October 2024.
Refer to market notice: 119495
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 27 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410271305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 October 2024 13:05
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 27 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 27 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:
[1.] From 1800 hrs 28/10/2024 to 1930 hrs 28/10/2024.
The forecast capacity reserve requirement is 1058 MW.
The minimum capacity reserve available is 798 MW.
[2.] From 2000 hrs 28/10/2024 to 2130 hrs 28/10/2024.
The forecast capacity reserve requirement is 1048 MW.
The minimum capacity reserve available is 779 MW.
Manager NEM Real Time Operations
[EventId:202410261500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 October 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 26 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Refer to market notice: 119441
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 26 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410261405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 October 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 26 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 26 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410261100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 October 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 26 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Refer to market notice: 119425
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 26 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410260915_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 October 2024 09:15
Issued by Australian Energy Market Operator Ltd at 0915 hrs on 26 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0915 hrs on 26 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.