CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 118311 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1145 hrs 18/09/2024.
No constraints were invoked during this event
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in the NEM regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
Duration: 0200 hrs 18/09/2024 until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.
The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Reclassification of a Non-Credible Contingency Event - QLD region - 30/04/2019
Cancellation of Reclassification of a Non-Credible Contingency Event: Nebo SVC and the Nebo No.2 275/132kV transformer - QLD region - 30/04/2019.
Refer AEMO Electricity Market Notice 68251
Based on advice from the participant, AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD
Equipment: Nebo SVC and the Nebo No.2 275/132kV transformer
Cancellation time: 1315 hrs 16/09/2024
Constraint set(s) revoked: Nil
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
At 1320 hrs 14/09/2024 there was a short notice outage of Braemar No2 330 kV / 275 kV Transformer.
The following constraint set(s) invoked at 1320 hrs 14/09/2024
Q-BRTX2
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0098210 | Cancelled | Production | AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.
The outage has been completed and Armidale - Sapphire 8E 330 KV Line returned to service at 1600 hrs 13/09/2024
Constraint set(s) revoked: N-ARSR_8E, N-TW_SVC
Manager NEM Real Time Operations
CHG0091340 | Cancelled | Production | QLD Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Market Network
Change Title: QLD Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600