Market Notices

119240MARKET INTERVENTION23/10/2024 04:01:16 PM

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119198


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 23/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0730 hrs 24/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1930 hrs 24/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119239MARKET INTERVENTION23/10/2024 02:57:50 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119205

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 2000 hrs 23/10/2024.

The direction update is issued at 1455 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119238MARKET INTERVENTION23/10/2024 07:59:50 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119260

Direction is cancelled from: 2000 hrs 23/10/2024

Manager NEM Real Time Operations
     
119237MARKET INTERVENTION23/10/2024 03:59:40 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119199

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/10/2024.

The direction update is issued at 1600 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119205MARKET INTERVENTION23/10/2024 08:31:53 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119200

The updated required actions: Synchronise and follow dispatch targets at 0845 hrs 23/10/2024

The direction update is issued at 0830 hrs 23/10/2024.

Manager NEM Real Time Operations
     
119200MARKET INTERVENTION22/10/2024 04:40:52 PM

Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119195


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 22/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 23/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 24/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119199MARKET INTERVENTION22/10/2024 04:39:32 PM

Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/10/2024 to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 119195


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1630 hrs 22/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 23/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 24/10/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
119198MARKET INTERVENTION22/10/2024 04:41:55 PM

Direction - SA region 22/10/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/10/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 22/10/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
119195MARKET INTERVENTION22/10/2024 03:07:59 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 119185

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 23/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 22/10/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm