115424INTER-REGIONAL TRANSFER01/03/2024 05:37:17 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/12/2023

Refer AEMO Electricity Market Notice 115398.

Constraint set CA_BRIS_54F2D1C0 revoked 1710 hrs.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1


Manager NEM Real Time Operations
115419INTER-REGIONAL TRANSFER01/03/2024 04:22:02 PM

Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024

At 1515 hrs 01/03/2024 there was a short notice outage of Para - Roseworthy 132 kV Line.

The following constraint set was invoked at 1530 hrs 01/03/2024
S-PARS

This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115408INTER-REGIONAL TRANSFER01/03/2024 08:15:32 AM

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024

At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.

Constraint set(s) invoked: N-MPTX

The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115398INTER-REGIONAL TRANSFER29/02/2024 07:06:55 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_54F2D1C0 from 1850 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
115372INTER-REGIONAL TRANSFER29/02/2024 04:18:08 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 29/02/2024

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA-BRIS_54F2ABFD_1 from 1610 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
115296INTER-REGIONAL TRANSFER28/02/2024 03:25:40 PM

Inter-regional transfer limit variation - 275kV South Pine SVC - QLD region - 28/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -275kV South Pine SVC - QLD region - 28/02/2024

At 1425 hrs 28/02/2024 there was an unplanned outage of 275kV South Pine SVC.

Constraint set Q-SP_VC invoked from 1435 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1
NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115256INTER-REGIONAL TRANSFER28/02/2024 11:02:16 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/02/2024

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_54F10C1F from 1035 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S_MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
115196RECALL GEN CAPACITY27/02/2024 08:27:52 AM

Request for Generator Recall Information for 29/02/2024 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115195RECALL GEN CAPACITY27/02/2024 08:26:49 AM

Request for Generator Recall Information for 29/02/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm