112083RESERVE NOTICE08/12/2023 01:19:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:

[1.] From 1530 hrs 09/12/2023 to 1600 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1253 MW.

[2.] From 1830 hrs 09/12/2023 to 1900 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1239 MW.

Manager NEM Real Time Operations
112082RESERVE NOTICE08/12/2023 01:10:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

From 1630 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1070 MW.


Manager NEM Real Time Operations
112075SETTLEMENTS RESIDUE08/12/2023 11:20:28 AM

[EventId:202312081120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 11:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1120 hrs on 8 December 2023

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.

Refer to market notice: 112063

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 8 December 2023.

This is an AEMO autogenerated Market Notice.
112063SETTLEMENTS RESIDUE08/12/2023 10:16:32 AM

[EventId:202312081015_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 10:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 8 December 2023

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1015 hrs on 8 December 2023.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
112057RESERVE NOTICE08/12/2023 05:21:05 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112052 is cancelled at 0515 hrs 08/12/2023.

Manager NEM Real Time Operations
112052RESERVE NOTICE08/12/2023 04:17:40 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1361 MW.


Manager NEM Real Time Operations
112050INTER-REGIONAL TRANSFER08/12/2023 01:18:51 AM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

Refer AEMO Electricity Market Notice 112048

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 0115 hrs.

Manager NEM Real Time Operations
112049INTER-REGIONAL TRANSFER08/12/2023 01:17:46 AM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 112047

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 0115 hrs.

Manager NEM Real Time Operations
112048INTER-REGIONAL TRANSFER08/12/2023 12:22:34 AM

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 0025 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1