Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024
Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1780 MW
The minimum capacity reserve available is 1446 MW
Manager NEM Real Time Operations
[EventId:202406141440_review] Prices for interval 14-Jun-2024 14:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141435_review] Prices for interval 14-Jun-2024 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141430_review] Prices for interval 14-Jun-2024 14:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1425 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141425_review] Prices for interval 14-Jun-2024 14:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1420 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141420_review] Prices for interval 14-Jun-2024 14:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141415_review] Prices for interval 14-Jun-2024 14:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406111900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 June 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 11 June 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.
Refer to market notice: 116955
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 11 June 2024.