Filter by category
Filter by Date
QNI Minor testing (NSW to Qld) 28th August 2024
Refer to market notice 117650
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Wednesday 28th August 2024 from 1300 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
[EventId:202408271910_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 August 2024 19:10
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 27 August 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 August 2024.
Refer to market notice: 117905
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1910 hrs on 27 August 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202408271810_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 August 2024 18:10
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 27 August 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 August 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1810 hrs on 27 August 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - VIC Region - 27/08/2024
Network Augmentation Commissioned - VIC Region - 27/08/2024
Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.
Manager NEM Real Time Operations
[EventId:202408271605_review] Prices for interval 27-Aug-2024 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 27 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408271600_review] Prices for interval 27-Aug-2024 16:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1555 hrs on 27 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 16:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408271555_review] Prices for interval 27-Aug-2024 15:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 27 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 15:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408271550_review] Prices for interval 27-Aug-2024 15:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 27 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 15:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408271545_review] Prices for interval 27-Aug-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 27 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.