121739INTER-REGIONAL TRANSFER12/12/2024 01:37:40 AM

Inter-Regional Transfer limit variation - Basslink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector.

The following constraint set was invoked at 0130 hrs 12/12/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
121734RESERVE NOTICE12/12/2024 12:42:05 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.

[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121716MARKET SYSTEMS11/12/2024 02:53:46 PM

CHG0100201 | Planned maintenance affecting the AEMO Market Network ***Outage Updated***

Change Number: CHG0100201
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 16/12/2024 08:12:00 AEST
Outage 1 End Date & Time: 16/12/2024 08:13:00 AEST
Outage 2 Start Date & Time: 16/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 16/12/2024 15:13:00 AEST

Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 08:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121710MARKET SYSTEMS11/12/2024 08:34:18 AM

CHG0100220 | Completed | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Number: CHG0100220

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System_PreProd

Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
121696MARKET SYSTEMS10/12/2024 04:15:03 PM

CHG0100201 | Production | Planned maintenance affecting the AEMO Market Network

Change Number: CHG0100201

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MarketNet

Change Title: Planned maintenance affecting the AEMO Market Network.

Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage Start Date & Time: 16/12/2024 15:12:00 AEST
Outage End Date & Time: 16/12/2024 15:13:00 AEST

Environment: Production

Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 07:30AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121695INTER-REGIONAL TRANSFER10/12/2024 03:31:22 PM

Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024

AEMO ELECTRICITY MARKET NOTICE
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1, N-Q_MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121691MARKET SYSTEMS10/12/2024 02:53:04 PM

CHG0100257 | Production | MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services

Change Number: CHG0100257

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services.

Change Start Date & Time: 12/12/2024 14:00:00 AEST
Change End Date & Time: 12/12/2024 16:00:00 AEST
Outage Start Date & Time: 12/12/2024 15:00:00 AEST
Outage End Date & Time: 12/12/2024 15:01:00 AEST

Environment: Production

Participant Impact and Requirements: During there change, there will be a 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Norwest will not be affected during this time.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121688INTER-REGIONAL TRANSFER10/12/2024 01:00:33 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1, N-Q_MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121682PRICES UNCHANGED09/12/2024 06:07:18 PM

[EventId:202412091735_confirmed] Prices for interval 09-Dec-2024 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 9 December 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2024 17:35.

In accordance with Market Notice 121671 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     